Material Backflush Hierarchy for Job Closing Process
The following is the material backflush hierarchy logic for the Job Closing process:
- If job material is linked to a Planning Contract, then uses the warehouse/bin if defined for the Planning Contract.
- If Job Material is related to an Operation go to step 3.
- Uses the input warehouse/bin (Input Warehouse and Bin fields located on the Resource Group Maintenance > Detail sheet) of the Resource Group related to an operation of job material and if the available quantity on hand is greater than zero.
- Uses the backflush warehouse/bin (Backflush Warehouse and Bin fields located on the Resource Group Maintenance > Detail sheet) of the Resource Group related to an operation of job material.
- Uses the Primary Bin defined in the primary bin field located in Warehouse Maintenance for the associated job material warehouse regardless of the unit of measure for the component part being backflushed.
- Uses First Part Bin associated to the job material warehouse regardless of the unit of measure for the component part being backflushed.
- Select the job material warehouse and look for a valid Bin.
- Uses the Primary Bin defined in Site of the Warehouse selected from step 7.
- Uses the First Bin associated to the job material of warehouse selected from step 7.
- Uses the First Bin of the Warehouse selected from step 7.
- Uses the First standard type Bin of the Warehouse selected from step 7.
- Do not backflush.
Material Backflush Hierarchy for Labor Entry Process
Backflush material quantities are reported complete at the job operation level. When the Epicor application performs material backflushing at the job operation level, it uses the following hierarchy to determine how the associated component materials should be backflushed, after labor is entered:
- If job material is linked to a Planning Contract, then uses the warehouse/bin if defined for the Planning Contract.
- Uses the input warehouse/bin (Input Warehouse and Bin fields located on the Resource Group Maintenance > Resources > Detail sheet) of the Resource used to report labor to the job operation and if the available quantity on hand is greater than zero.
- Uses the input warehouse/bin (Input Warehouse and Bin fields located on the Resource Group Maintenance > Detail sheet) of the Resource Group used to report labor to the job operation and if the available quantity on hand is greater than zero.
- Uses the backflush warehouse/bin (Backflush Warehouse and Bin fields located on the Resource Group Maintenance > Resources > Detail sheet) of the Resource used to report labor to the job operation.
- Uses the backflush warehouse/bin (Backflush Warehouse and Bin fields located on the Resource Group Maintenance > Detail sheet) of the Resource Group used to report labor to the job operation.
- Uses the Primary Bin defined in the primary bin field located in Warehouse Maintenance for the associated job material warehouse regardless of the unit of measure for the component part being backflushed.
- Uses a Part Bin associated to the job material warehouse using the same tracking UOM for the component part being backflushed and if the available quantity on hand is greater than zero.
- Uses the First Bin in the job material warehouse that has an available quantity, regardless of unit of measure.
- Do not backflush material.