1.oracle ERP 版本:12.0.6
2.问题描述:
刚刚建立物料,还没有来得及建立工序的工单,其状态为未发放,
这时对组件变更实施ECO,组件需求日期全部为空,ECO过程中也是正常的,但ECO实施的结果不起作用;
3.问题发现过程:
一天计划员向我反映一张工单的物料需求在Item Supply/Demand查询不到。
于是我就去查找原因,发现工单组件需求日期为空,接着分析所有此问题的工单中,
共性是没有工序,从部分工单组件Request id发现之前刚执行过ECO。
大致推断工单没有工序,实施后ECO导致的,在测试区做一下,果然是这样的。
4.受影响的业务:
由于工单组件需求日期为空,所以工单组件的需求在Item Supply/Demand查询不到,
当然MRP也不会计算进来,工单物料齐套性受到影响。
5.临时解决方式: 就是把工单再次发放时,要把清单版本日期清空保存。
6.Oralce 最终解决方案。
=== ODM Solution /Action Plan ===
To implement the solution, please execute the following steps:
1. Download and review the readme and pre-requisites for Patch.8463132:R12.WIP.A.
2. Ensure that you have taken a backup of your system before applying
the recommended patch.
3. Apply the patch in a test environment.
4. Confirm the following file versions:
=== ODM Proposed Solution Justification ===
The issue is resolved by upgrading to the following file versions or higher.
wipbmrts.pls 120.2.12000000.1
wipbmrtb.pls 120.15.12000000.5
5. Retest the issue.
6. Migrate the solution as appropriate to other environments.
来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/41594/viewspace-623789/,如需转载,请注明出处,否则将追究法律责任。
转载于:http://blog.itpub.net/41594/viewspace-623789/
在Oracle ERP 12.0.6版本中,遇到新建物料未设工序工单状态下实施ECO,导致组件需求日期丢失,进而影响物料需求可见性及MRP计算的问题。通过分析,发现工单无工序是ECO失效的原因。临时解决办法为重新发放工单并清空清单版本日期。最终解决方案涉及应用补丁8463132,升级特定文件版本。